Project Management Professionals (PMP) Exam 7

Certified Project Management Professional (PMP) Practice Exam Questions with Answers

Practice the Project Management Professionals (PMP) Exam 7 past questions and answers. Our experts have answered the questions and you will get the correct answers to the Project Management Professionals (PMP) Exam 7 questions. Prepare yourself for the exam ahead and test your knowledge and readiness..

0%
0 votes, 0 avg
1

Project Management Professionals (PMP) Exam 7

PMP

Project Management Professionals (PMP) Exam 7

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 40

Collecting requirements for the project and creating the WBS has been a daunting task because stakeholders' needs are vague and are only expressed in the most general terms due to the nature of the project. As a result of this uncertainty, the project manager is concerned about excessive changes, wasted work, and rework anticipated during project execution.

What is the project manager's best course of action?

2 / 40

A project manager implements the project management plan meticulously but is struggling with leading the project team effectively. There is a great deal of unhealthy tension between the project team members as well as with the project manager. The project manager has had several outbursts during sprint retrospectives, which has caused the meeting to be abruptly adjourned.

What should the project manager do first?

3 / 40

At times over a project life cycle, the team must adopt a few agile ceremonies. The aim is to communicate quicker in times of tight deadlines. Unfortunately, team members are not getting the information needed during the ceremonies.

What is the best option to confirm that the information is received and understood?

4 / 40

You want to recognize the contributions of some of the high-performing team members so far in the project.

Which of the following do you need to guide you through this process?

5 / 40

A project manager is leading a daily standup meeting with a scrum team as part of the Direct and Manage Project Work process. A developer raises an impediment stating that he is struggling with the software code necessary to authenticate users on the sign-in page. The developer indicates that the impediment could result in a schedule delay to the current sprint.

What is the project manager's best course of action?

6 / 40

You are managing a project to construct a bridge at a location that is highly regulated by multiple levels of government. You are in the process of developing a plan that will establish the criteria and the activities for developing, monitoring, and controlling the schedule.

Which of the following should you gather to complete this process?

7 / 40

Projects in a program are using various project management approaches, such as plan-driven, agile, hybrid. The project teams are complaining that because of that, the team members must enter the same work, hours, risks, and other data in multiple tools. The redundant work is impeding on their productivity time.

What is the best course of action for the program manager?

8 / 40

The scrum master, business analyst, programmers, and testers have been assigned to a product development project. The performing organization is well-versed with the traditional waterfall framework but will incorporate scrum for the software development phase of the project.

What is the best strategy to ensure that all of the scrum roles and responsibilities are served in the project?

9 / 40

In a pharmaceutical project, human trials have been started. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week.

What should the project manager do first?

10 / 40

Senior leadership has returned from a conference where they have learned about the agile practice of retrospectives. Even though the organization does not manage any projects in an agile manner, they mandate that from now on this ceremony is included in all projects.

How should the outputs from the retrospectives be stored and managed?

11 / 40

You are establishing the relative priorities of individual risks identified in the project.

Which of the following tasks is the least likely to impact this prioritization?

12 / 40

You are conducting a sprint retrospective in accordance with the communications management plan. The development team members want to try pair programming as they believe it will improve productivity by reducing rework. Even though you are very skeptical, you agree to implement the practice as you want to empower the team to be a self-managing unit.

What should you do next?

13 / 40

Not all team members are properly checking out resources used in the project.

What is the best option for the project manager?

14 / 40

You are leading a project to design a high-efficiency solar cell. The project needs copper, silver, and silicon among other materials. You have ordered custom-built manufacturing equipment, secured permission to install a solar array on the roof for testing, and reserved a conference room for daily stand-up meetings.

What is the result of your efforts?

15 / 40

Two team members are arguing over how to organize the work packages in the work breakdown structure (WBS). One says the work packages should be arranged in the order the work is planned to be carried out, while the other insists the order of the work packages in the WBS does not matter. The two ask the project manager for advice.

What is the project manager's best response?

16 / 40

As part of the Direct and Manage Project Work process, the project manager conducts an iteration planning meeting. The meeting is dominated by the most senior developer who frequently and sharply interrupts the other team members. The project manager wants to ensure that during the next iteration planning meeting all voices are heard.

What is the project manager's best course of action?

17 / 40

A project is six months into its nine-month projected duration. The project manager reports that the project is at least three months behind schedule because certain key stakeholders were resistant to consequential changes due to the project.

What might have been done differently during project planning to avoid this situation?

18 / 40

Midway into project execution, new cybersecurity laws take an immediate effect and require audits of the system. The project has a well thought out project management plan. The audits may come at any time throughout the system?s development.

What is the best way for the project manager and team to address the risk of audits disrupting the project plans?

19 / 40

One of the project activities requires that a search of a large area is conducted to find debris from an explosion of a failed prototype. The project is now in planning, and there is a debate among the team members on the type and quantity of resources needed to complete this activity.

What should the project manager do first?

20 / 40

A plan-driven project has many deliverables planned to be released at the end of the phase. The project manager wants to ensure that the deliverables are completed as expected.

Which agile practices can the project manager recommend to the team to make certain that the deliverables are completed and delivered as expected?

21 / 40

You are in the process of developing an approximation of the monetary resources needed to complete project work for a large-scale multinational project which will take at least seven years to complete. Your previous projects have all been domestic with short timeframes.

As part of the process you are currently performing, what might you need to do differently compared with your past projects?

22 / 40

A project manager is developing a cost management plan and needs to determine the best source of funding for a project that is dictated by a legal requirement. The cost of capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for self-funding. The NPV of the project is $500,000, and the opportunity cost is $750,000.

What is the project manager's best course of action?

23 / 40

You are assigned to a software development project, and you are conducting a product review with an important client. Although the deliverables were previously verified, the client detects a defect and rejects one of the deliverables.

What should you do?

24 / 40

An organization is to undertake a multi-phased project. The sponsor wants to pursue the project objectives as they have been planned but also wants to accommodate and adjust to new information and changes in the environment as the project progresses.

Which project management approach should the project manager select for this project?

25 / 40

As part of the Plan Resource Management process, project team members hold a brainstorming session to charter working agreements. The team identifies 37 agreements that include communication guidelines, decision-making and conflict resolution processes, core hours, a definition of a story point, how and when user stories will move through the Kanban board, etc.

What should the project manager do next?

26 / 40

Your sponsor has committed to building a high-speed rail from one major inland city, Azules, to the coast. You have two possible routes, either Brazos or Corazon.

Given the costs, odds, and rewards of high demand and low demand of each route in this decision tree, what is the expected monetary value of the route to Brazos?

650814a

27 / 40

Following is an illustration of a project network activity node that includes some information about activity D.

Given the information provided, what is the total float of activity D?

614007 A

28 / 40

The project team is undergoing an agile transformation. This requires the team members to maintain their original project plans in the current management tool, but also enter performance data in the new tool built around agile practices. The team identifies that the information in the two tools is out of sync. This risk has been identified earlier in project planning.

What is the best course of action for the project manager?

29 / 40

The construction project has many people and specialized teams at the worksite every day. Frequent communication between the team leads is critical for safety and efficiency.

Which agile ceremony can this project incorporate to increase timely cross-functional communication?

30 / 40

The organization?s leadership wants projects to include more agile methodologies.

Before mandating any agile methods to be used in a project, what should be done first?

31 / 40

To produce the deliverables, the project will procure goods and services from outside the organization. The project manager has instructed the team to develop a comprehensive list of individual project risks related to those procurements.

What is the best course of action for the project team?

32 / 40

Team members are frequently changing during the long timeline of a multi-phase project. The project manager is questioning whether to include agile practices to accommodate the changes.

What should the project manager do prior to moving to a hybrid approach?

33 / 40

A project manager is wrapping up the hardware development phase of a product development project. The project will now transition to the software development phase.

How might the project manager's role change with respect to integration management?

34 / 40

A project manager is implementing the requirements management plan for a software upgrade project that will incorporate some agile elements. The project manager needs to quickly define cross-functional requirements and reconcile stakeholder differences to build a consensus among the relevant stakeholders.

What is the project manager's best course of action?

35 / 40

During project execution, several unexpected issues have developed and are now threatening the project schedule and budget.

What is the best course of action for the project manager to address the issues?

36 / 40

A project manager facilitates a discussion with the team about experimenting with some agile practices in their plan-driven project. A suggestion of incorporating daily standups is on the table. The team members, however, are unsure of what is expected of them.

What can the project manager suggest the project team members do prior to the daily standup?

37 / 40

Your project team members are writing software code together as a pair and reviewing each other's work to determine if the code conforms to the requirements documentation.

Which of the following will be a result of these reviews?

38 / 40

You are managing a renovation project of a house which is to be completed at a budget of $100,000. Earned value analysis shows that so far you have completed 40% of the work and spent $60,000.

How much more will it cost to complete the project if the cost performance remains unchanged?

39 / 40

The resource management plan for an international project calls for a scrum team to be colocated during the regular workweek. However, after five sprints were completed, the project manager got a change request approved to cut costs by transitioning the team to a virtual environment working remotely from their homes with the start of the sixth sprint.

After the team begins working remotely, what will be the best method to understand the impact of the change on the team's productivity?

40 / 40

A major dispute arises with a vendor on a project. The project manager claims that the vendor has failed to perform its contractual obligations, while the vendor complains that the project is behind on payments.

What is the best course of action for the project manager in this situation?

Your score is

0%

See also:

CAPM Exam 8 – Project Cost Management Questions with Answers

CAPM 7 – Project Time Management Questions with Answers

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!
Scroll to Top