Project Management Professionals (PMP) Exam 6

Project Management Professionals (PMP) Exam 6 Past Questions & Answers.

Practice the Cisco Certified Network Associate (CCNA) Exam 4 past questions and answers. Our experts have answered the questions and you will get the correct answers to the Cisco Certified Network Associate (CCNA) Exam 4 questions. Prepare yourself for the exam ahead and test your knowledge and readiness.

0%
0

Project Management Professionals (PMP) Exam 6

PMP

Project Management Professionals (PMP) Exam 6

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 40

You are in the process of establishing a knowledge management system for your project.

Which of the following actions will be the least beneficial in this process?

2 / 40

A project manager is in the process of obtaining team members. She wants to understand the availability of the team members required to complete project work.

What should the project manager do to find this information?

3 / 40

You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle.

With the project life cycle selected, how will the product be delivered?

4 / 40

You are part of a cross-functional development team piloting an adaptive approach to project management in an organization that has traditionally used a predictive approach. You realize that you have to tailor the template of the schedule management plan.

Which of the following components of the template are you likely to tailor the most?

5 / 40

A project team is using the Stacey Complexity Model to map the degree of uncertainty in the project and select the appropriate project life cycle. As the meeting progresses, it becomes evident that while the requirements are well-known, the team is unfamiliar with the technology required to implement them. As a result, the team selects an adaptive project life cycle.

Where on the Stacey Complexity Model did the team most likely map the project?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the simulator, we are asking you to select the answer below.)

6113179

6 / 40

You have been asked to lead a product development project which will use an agile framework. Currently, you are in the process of drafting the project charter, and you want to bring together stakeholders and subject matter experts to discuss perceived project risk, success criteria, and other topics.

What is the best way for you to accomplish this objective?

7 / 40

You are leading a project to build an oil pipeline in a foreign country. You want to outsource some of the construction work to local contractors and are in the process of preparing the bid package for prospective sellers.

Which of the following documents would you leave out of the package?

8 / 40

To define the product that will be produced by the project, the project team is using a product analysis technique that helps with breaking down the high-level requirements into the level of detail needed to design the product.

Which of the following is the product analysis technique used by the team?

9 / 40

You are developing the risk management plan for your project. In support of this process, you need to determine the acceptable level of overall project risk exposure.

What should you do first?

10 / 40

A project is nearing its end when the project manager receives an approved change request to replace a defective unit.

What should the project manager do next?

11 / 40

A corporate restructuring project is in execution. The job responsibilities of many key stakeholders are being disrupted, which has caused challenges in keeping the stakeholders engaged in a positive manner.

Which of the following actions is the project manager least likely to perform in this situation?

12 / 40

As a project manager, you are in the process of estimating the team resources that will be required for your project. The challenge you are having is that, due to the nature of the project and the selected development approach, only a few of the top levels of the WBS have been identified with the remainder to be progressively elaborated throughout the project.

What is the best approach to determine the team resource requirements for the project?

13 / 40

A servant leader has just been assigned to an upcoming product development project and believes that the project is well-suited to Kanban. However, the development team is unfamiliar with this approach.

What is the servant leader's best course of action?

14 / 40

A multi-phase project has reached a phase gate. The key project stakeholders want to determine if the phase has met its success criteria and if the project should proceed to the next phase.

In addition to the project management plan, which documents will be required?

15 / 40

A team member volunteered to provide the project status update in a weekly presentation to the key stakeholders. After the first meeting has taken place, feedback from the stakeholders suggests that the presentation was not very engaging.

What is the best way for the project manager to address this situation with the team member?

16 / 40

During a bidder conference, a supplier asks why a section is missing from the request for quotation (RFQ). Upon realizing that the section is indeed missing, the project manager becomes flustered and stumbles through a brief reply. When the seller responses were received, all but three prospective suppliers fail to address the missing section.

What is the best course of action?

17 / 40

During a daily stand-up meeting, one of the programmers mentions that she had some extra time and added functionality, which was not included in the original design. She believes the customer will appreciate the added functionality.

What is your best course of action?

18 / 40

During an inspection of a project deliverable, the team detects the same defect in the deliverable that has already been identified during a previous inspection. The project manager is confused about how this could have happened since a change request was approved to repair the defect. After discussing the issue with the team, the project manager learns that the team never implemented the approved change request.

What could have helped prevent this situation?

19 / 40

You are leading a project to develop a new web application. Together with your project team you reprioritize the product backlog, determine velocity for the past iterations, and adapt your work plans accordingly. Additionally, you facilitate retrospectives every two weeks.

Which of the following processes describes the work you are performing?

20 / 40

A project team performs monthly risk audits for a project, where a large number of identified risks have been realized. So far, the risk responses have been appropriate, and the reserves sufficient. An executive for the requesting organization criticizes the project manager improper risk audits, stating that only independent, external resources should perform risk audits.

How should the project manager respond?

21 / 40

The following Gantt chart displays the schedule for a software upgrade project. The system analysis was completed on August 12th, but the system design and development activities are still in process as of October 3rd. Once the product is developed, the project team will need to test and deploy it, which must be completed by October 17th. The method used to determine the earned value is based on percent complete.

What is the cost variance as of October 3rd?

625134

22 / 40

A project is behind schedule because department managers reassigned project team members to work on other assignments. After negotiations with the managers, you agreed to a temporary solution where a core group of project resources is dedicated to performing the project work until more resources are approved.

What conflict resolution technique did you most likely employ in this situation?

23 / 40

A three-phase project to build a prototype is underway. The first phase entails design. In the second phase, the manufacturing team would produce the parts from the design specifications. In the third phase, the production team would assemble the parts to construct the prototype. The project is now at the end of the first phase.

What should be done with the phase's deliverables?

24 / 40

A technician has just tested a piece of equipment and found a defect. The technician has informed the project manager and submitted a change request to repair the defect, indicating that the repair will require significant rework.

What should the project manager do first?

25 / 40

The team has just reported to you that they have completed the Plan Quality Management process. You review their work and see that they have produced the quality management plan, and made the necessary updates to the project management plan and project documents.

What did they forget?

26 / 40

At the end of a design project, a competitor has gained market share with a new technology that has rendered the project?s deliverable obsolete. The project sponsor is pleased with the work of the project team who finished within budget and on time but thinks that the project should have been terminated much sooner.

What might have the manager of the project done differently in this situation?

27 / 40

You are part of a project team designing a new type of a vehicle. You are about to begin work on a work package for the braking system of the vehicle and want to review the acceptance criteria before starting the work.

Where can you find this information?

28 / 40

The project manager is managing the research and development of a new cancer screening test. The project manager would like to determine whether the processes currently in use in the project are effective in meeting the quality requirements specified by the customer.

What does the project manager need to obtain first to make this determination?

29 / 40

A project team is mulling over two risk responses for inclusion in the risk register. The first risk response has two criteria that must be met and costs $5,000. The second risk response has four criteria that must be met, but only costs $2,000.

What action is the project team least likely to take in selecting the best risk response?

30 / 40

You are leading a large project that involves many stakeholders. You want to get two new team members up to speed with the overall dynamics of the project and engage effectively with the project stakeholders.

What should you do?

31 / 40

You are managing a project to build a house for a private client. A few weeks before the project's planned completion date, the client calls and asks to add an outdoor sauna to the property. You analyze the project schedule and determine that this change would be fairly easy to implement without having an impact on the completion date.

What should you do first?

32 / 40

During project planning of a large, complex project, project management best practices were rigorously and thoroughly followed. During project execution, the project experienced several critical risks, which were foreseen and previously identified. Despite the meticulous planning, the project failed to achieve the established objectives due to these realized risks.

What may have gone wrong in this scenario?

33 / 40

A project to reduce the defect rate of the manufacturing process is underway. To analyze and improve the process, the project team is now carrying out the quality assurance activities.

Which of the following would be the most beneficial for this project?

34 / 40

A project to construct an assembly line is nearly complete. The project manager closes procurements, shares the final project report, updates the lessons learned repository, and obtains feedback from the relevant stakeholders.

What should the project manager do next?

35 / 40

You are developing the communications management plan for a construction project. You want to determine the information needs of the project stakeholders, specifically focusing on the type and the format of information that will be required to communicate with the stakeholders.

What is your best course of action?

36 / 40

A project is underway to construct a wind farm in an area with no communication infrastructure. The plan is to monitor progress and coordinate the scheduling of the project activities using project management software and provide daily status updates to the project sponsor at the home office. Two project teams will work and reside onsite in rotating seven-day tours.

Which of the following is the most likely challenge the teams will face while controlling the schedule?

37 / 40

To acquire resources for the project, the project manager consults the resource management plan. The plan calls for the scrum master to be assigned to the team. However, the only individual in the company qualified to serve as a scrum master has already started working on another project, and her functional manager does not cooperate on a potential resolution.

How could this situation have been prevented?

38 / 40

You are facilitating a meeting with your project team to develop the team charter. At the start of the meeting, a team member states, "I don't understand the importance of this meeting. We are all professionals, and this isn't our first project working together. Wouldn't our time be better spent getting an early start on project execution?" The body language of the other team members suggests that they agree with the comments.

How should you respond to the team member?

39 / 40

You are developing the project scope statement. You have specified the deliverables for the project, included the requirements under which the deliverables will be accepted, and explicitly stated what is out of project scope.

What else should you include in the project scope statement?

40 / 40

You are leading a software development project where the developers are colocated within rented office space. Writing the code is taking longer than anticipated, and you have contacted the landlord requesting to rent the office for another week. Unfortunately, the landlord tells you that the office is already booked. You capture the problem in the project documents.

What should you do next?

Your score is

0%

See also:

CAPM Exam 8 – Project Cost Management Questions with Answers

CAPM 7 – Project Time Management Questions with Answers

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!
Scroll to Top