Project Management Professionals (PMP) Exam 5

Practice the Project Management Professionals (PMP) Exam 5 past questions and answers. Our experts have answered the questions and you will get the correct answers to the Project Management Professionals (PMP) Exam 5 questions. Prepare yourself for the exam ahead and test your knowledge and readiness..

0%
PMP

Project Management Professionals (PMP) Exam 5

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 40

While performing project work, a team member notices that there is a potential new risk, which could impact the project's critical path.

What should the team member do immediately?

2 / 40

You have just taken over a project in execution. During your first week, you determine that the project team members spend a lot of time responding to unexpected requests for information from different project stakeholders. Because of these interruptions, the team cannot focus on their project activities, and as a result, the project is behind schedule.

What should you do first?

3 / 40

As you are monitoring the cost baseline for your project, you notice that project expenses are higher than expected at this point in the project.

What is the most likely cause of the variance?

4 / 40

While reviewing your project's performance, you discover a significant variance. If the issue is not fixed before the next customer inspection, your project might be canceled. However, after a further review conducted by the project team, you are glad to hear that bringing the project back on track requires only a minor correction to a configuration element.

What should you do first?

5 / 40

A company is considering two projects, Alpha and Beta. Project Alpha is expected to result in a $50 million net profit, while project Beta and is expected to net $45 million. Both projects could be very lucrative and rewarding. However, the financial controller has stated that the company can only invest in one of these projects.

If project Alpha is selected, what will be the opportunity cost?

6 / 40

You are managing a project that is nearing its end and planning to settle all pending claims with the vendors. In one case, you are not satisfied with the delivery of their final product. All conversations with the vendor have ended in an impasse.

What should you do in this situation?

7 / 40

The project is in execution, but your project team is unable to stop arguing about the project milestones and the specific risks associated with them. This on-going conflict puts the project at risk of running behind schedule.

What would likely have helped avoid this conflict had it been properly created first?

8 / 40

Recently, you promoted your star programmer, Sam, to lead the agile development team. Sam was a fantastic software coder, and you thought the promotion would mean that he could now share his expertise with the other development team members. However, you are surprised to learn that the performance of Sam in his new role is not meeting your expectations.

Which empirical rule did you forget while considering the promotion of Sam?

9 / 40

You are managing a project to build five bridges. The project consists of five sequential phases with each phase delivering one bridge.

After the first phase of the project is complete, which process group of the second phase should follow?

 

10 / 40

In the design phase, external experts verified that the team's blueprints for a new crane complied with requirements. During the build phase, the customer performed a walkthrough and found that some welding joints on the crane were defective. The crane needs to be reworked to ensure it can be operated safely.

How could this situation have been avoided?

11 / 40

The project management plan specifies that a predictive development approach has been selected to produce the project deliverables.

Where in the project life cycle will the overall project risk be the lowest?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the simulator, we are asking you to select the answer below.)

6113151

12 / 40

Your project has been plagued with numerous change requests.

What is the most likely reason?

13 / 40

Your company was awarded a contract that includes a 10% bonus payment if the project is completed two months early. You consider several options to exploit this opportunity.

What is the best course of action for you to increase the chances of receiving the bonus?

14 / 40

You are facing problems decomposing the testing work package into the final activities required to complete the work package. Detailed testing plans and activities cannot be determined until the system is at least 50% developed and more details become available. The system development work package will take at least three months to complete.

What is the best way to resolve this problem?

15 / 40

A team member submits a draft of the requirements management plan to the project manager for a review. The project manager notices that one of the components included in the plan does not belong there.

Which of the following components did the project manager most likely notice?

16 / 40

You have compiled a list of potential stakeholders for your project, and now you are classifying the stakeholders with regard to the direction of their influence. As you work through your way down the list of stakeholders, you have come to the project sponsor.

How should this stakeholder be classified?

17 / 40

During project execution, the team discovers that some of the buttons on the remote control developed by the project for a new product do not work according to the specifications. A change request is submitted and approved to replace the buttons.

Which of the following best describes this change request?

18 / 40

The project aims to investigate the feasibility of constructing a hydroelectric dam from a technical, economic, and social point of view. The project charter created by the project manager on behalf of the project sponsor is now approved.

Which of the following processes should be performed next?

19 / 40

An organization has a project management office (PMO) that ensures all relevant project documents are created, and all project management processes are followed according to established best practices.

What should the project manager review first to identify stakeholders for a newly started project?

20 / 40

he following table is an activity list that includes the duration and predecessor for a series of project activities.

What is the duration of the critical path?

612348 A

21 / 40

You are working with a team to estimate how much time is required for each activity. You are using a document that contains information on the categories of labor, material, and equipment required to complete the project. You are also interested in the skill levels, required certifications, and the grade levels for supplies.

Which of the following documents would you primarily refer to for this purpose?

22 / 40

You have been requested to fill in for a project manager who has called in sick midway into project execution. As you get yourself familiar with the project team, you are impressed to see how well the team members collaborate and work through issues smoothly and effectively.

Based on your observations, where is the team on the Tuckman ladder?

(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the simulator, we are asking you to select the answer below.)

6113170

23 / 40

You are managing a software upgrade project for your company. Your project sponsor has a great deal of authority regarding project decisions, but you recently discovered that he doesn't have much interest in your project. To complete the project successfully, you need your project sponsor's continuous support.

What stakeholder management strategy should you use with your project sponsor?

24 / 40

You have just taken over a project in which some of the deliverables will be produced by external vendors. You want to familiarize yourself with those who are involved in the project from the sellers' side.

Where would you look to obtain this information?

25 / 40

One of your contractors is not performing to the agreed-upon standards. You want to terminate the contract and engage another contractor for the same job. You need to determine the specific legal procedure for the early termination of the contract.

What should you do?

26 / 40

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.

What estimation technique does the project manager use?

27 / 40

A project manager does most of her communicating with team members, internal project stakeholders, and external project stakeholders via email. The project manager incorporates specific techniques when composing her emails to reduce any misunderstandings.

Which of the following is not considered one of these techniques?

28 / 40

A project is divided into four sequential phases. The second phase of the project has just been completed, and the third phase is about to begin.

What should the project manager do first?

29 / 40

An organization has a policy that a change control board (CCB) must review all change requests for every project in the organization, and that the CCB follows the recommended activities outlined in the PMBOK® Guide. Project managers and the project team do not serve as members of the CCB.

Based on this scenario, which of the following activities might be performed by members of the CCB?

30 / 40

The project sponsor asks for a copy of the document that contains the description, owner, source, priority, and status of product requirements.

Which project document is the project sponsor requesting?

31 / 40

As the project manager, you are leading a brainstorming session with key stakeholders to identify project risks. Once the project risks are determined, you immediately proceed to nominate different team members as risk owners and assign them the task of developing individual risk response plans.

Have you properly conducted risk management planning?

32 / 40

For an upcoming project, a needs assessment and business case have been completed, and the project management office (PMO) is reviewing a draft of the benefits management plan. The PMO highlights an element of the benefits management plan and requests that the element be removed before the document is finalized.

Which of the following was most likely the element the PMO requested to remove?

33 / 40

A project manager is in the process of developing the stakeholder register. As the first step in this process, she needs to create a list of potential stakeholders and decides to use a data gathering technique called brain writing.

What is the first thing to do when using that technique?

34 / 40

A project manager is performing quality assurance for a project whose quality standards are very stringent. In order to meet and exceed the quality requirements, the project manager uses a set of technical guidelines, which were applied during the design phase of the project to optimize quality.

What tool or technique is the project manager using in this scenario?

35 / 40

A company has authorized a dedicated change control board (CCB) to review and evaluate all change requests that are submitted for any project.

If the project sponsor is a member of the CCB, which of the following best describes an individual or group that can request a change on a project?

36 / 40

During project planning, the project team rigorously defined the project scope. During project execution, a senior engineer calls the project manager and suggests a simpler and more efficient design which could benefit the project.

What should the project manager do next?

37 / 40

A project manager is leading a process improvement project for a factory operation. Currently, the project manager and the team are performing the Monitor and Control Project Work process.

Which of the following activities might be carried out during this process?

38 / 40

You are managing a project to build a database and need to acquire information from the stakeholders of the project. The team is using brainstorming, focus groups, interviews, questionnaires, and benchmarking to understand and document the stakeholders' needs.

The methods the team is using are representative of which tool and technique?

39 / 40

The quality management plan specifies the use of a data representation technique to show the strength of relationships between four factors.

Which of the following tools or techniques should be used to comply with the plan?

40 / 40

You are about to start planning for a large and complex project. Due to the size of the project along with the regulatory and environmental considerations, the development of a detailed project management plan will be critical.

As a starting point for initial project planning, what is the first thing you should do?

Your score is

0%

See also:

CAPM Exam 8 – Project Cost Management Questions with Answers

CAPM 7 – Project Time Management Questions with Answers

CAPM Exam 5 – Project Scope Management Questions with Answers

Certified Associate in Project Management (CAPM) Exam 4

Certified Associate in Project Management (CAPM) Exam 3