CAPM Exam 8 – Project Cost Management Questions with Answers

Practice the CAPM Exam 8 – Project Cost Management past questions and answers. Our experts have answered the questions and you will get the correct answers to the CAPM Exam 8 – Project Cost Management questions. Prepare yourself for the exam ahead and test your knowledge and readiness.

0%
0 votes, 0 avg
0

CAPM Exam 8 - Project Cost Management Questions with Answers

Certified Associate of Project Management

CAPM Exam 8 - Project Cost Management Questions with Answers

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 50

You are managing a building project with a budget of $1,200,000 over a 12-month period. After 3 months, you have spent $400,000 and completed 25% of the project. What is the Estimate at Completion (EAC) assuming the current work efficiency?

2 / 50

You are a project manager for a homebuilding project. The project is halfway completed, but you realize that some of the cost calculations are incorrect because you were using traditional costing instead of activity-based costing. What should you do?

3 / 50

During the cost control process of a project, the project manager notices that the actual costs are consistently exceeding the planned budget. One of the team members suggests reducing scope to address the cost overrun. What is the best course of action for the project manager?

4 / 50

During Value Analysis of a software project, you notice that two different software libraries provide similar features but one is significantly more expensive than the other. What is the appropriate next step?

5 / 50

You are managing an ecological research project when a grant providing majority of your funding is suddenly revoked. As the project manager, how would you react to this sudden change in cost?

6 / 50

You've been given a project that requires an initial investment of $500,000, and is expected to bring an annual cash inflow of $100,000 for 5 years. The management wants to increase the ROI to 30% from the existing 20%. What changes should you incorporate into the project to achieve this target?

7 / 50

At the end of the first phase of your project, you notice actual costs are lower than estimated costs. What should you do?

8 / 50

You've discovered a major risk during a project that could lead to extra costs not accounted for in the budget. What should be your first step in response to the situation?

9 / 50

A project you are managing has an initial cost of $350,000 and is expected to generate a cash inflow of $120,000 every year. If your company's expectation is an ROI of 50%, what measures should you take?

10 / 50

During a Value Analysis in a construction project, you find a design change that can significantly lower costs but would result in a one-month delay. If the client's priority is to finish the project quickly, what should you do?

11 / 50

You are managing a project to install a set of energy-efficient appliances for a new hotel. These appliances are more costly at the installation phase but will result in sizeable energy savings across time. What is the most important element to consider while deciding upon the choice of these appliances?

12 / 50

Your project has an estimated cost of $80,000. Due to some unexpected natural calamity, it was required to incorporate additional safety measures leading an increase of 25%. What would be the new cost estimate?

13 / 50

You have been allocated some contingency funds for a project. During the project, you realize that some of these funds have been spent on non-emergency issues. What should you do?

14 / 50

A project requires an initial investment of $300,000, and has an expected annual cash inflow of $60,000 for 6 years. Under management instruction on increasing the ROI by 20%, what adjustments could be made to improve ROI?

15 / 50

You are in charge of a construction project with a total cost of $900,000 expected to last 9 months. After 3 months, you've spent $350,000 and only finished 30% of the project. What is the Schedule Variance (SV)?

16 / 50

You are managing a small-scale project. You notice that the cost of quality checking is not uniformly distributed but follows a pattern based on the type of activities. How would you incorporate this realization into activity-based costing?

17 / 50

In a project to build a new hospital, the local authority has suddenly introduced a new tax affecting the cost of the construction materials. As a project manager, how should you respond?

18 / 50

You are managing a research project. Halfway through the project, you realize that the cost of laboratory supplies has increased by 20%. What would be the most effective strategy for managing this situation?

19 / 50

You are handling a construction project. You realize that cost estimations are exceeding mainly due to miscalculation in the cost of laying the foundation. What would be an appropriate solution in this situation if you were implementing activity-based costing?

20 / 50

On calculating the cost performance index (CPI), you discover that it is higher than 1. However, several stakeholders are raising concerns about the escalating project costs. How should you approach the situation as a Project Manager?

21 / 50

You are managing a construction project with a total budget of $1,500,000 over 15 months period. After 5 months, you have spent $700,000 and completed only 40% of the project. What is the Cost Performance Index (CPI)?

22 / 50

You are managing a software development project. The project is at the final stage, and upon reviewing the costs, you notice a significant difference between the planned and actual indirect costs. As a project manager, what could have been a more effective cost management strategy?

23 / 50

During the cost estimation process, a project manager says that they will be using the Analogous Estimation technique to predict project costs based on historical data from a similar project. However, the team member suggests using Parametric Estimation instead, which relies on a predictive model to calculate costs based on identified parameters. What type of cost estimation technique is the team member recommending?

24 / 50

You are overseeing a construction project with a budget of $850,000 over a span of 10 months. After 5 months, you've spent $500,000 and completed 50% of the project. What is your Cost Variance (CV)?

25 / 50

You are overseeing a city infrastructure project with an initial estimated cost of $5 Million. Due to an unprecedented labor strike, an increase of 10% is anticipated. What is the new cost estimate?

26 / 50

A key supplier unexpectedly increases their prices mid-project causing project costs to rise. What is the best strategy you can use to minimize this risk in the future?

27 / 50

During project planning, a team identified a risk event with a high impact and low probability. What approach should the team use to mitigate this risk?

28 / 50

The client for your software development project has requested additional features, which could inflate the project's cost. As the project manager, what should be your best approach considering this new development?

29 / 50

While performing a Value Analysis, you found that a project team member is under-utilized. What should be your decision?

30 / 50

The team is designing a critical system with substantial operational costs. During the Value Analysis, you identified a new, untested part that could cut operational costs. What should be your next step?

31 / 50

You are working on a project that requires an initial investment of $350,000, which generates an annual cash inflow of $75,000. If the project lasts for 6 years, how does increasing the cash inflow by 30% change the ROI?

32 / 50

You are managing a project with an initial investment of $800,000 and expected annual cash inflows of $200,000. The project is expected to run for 4 years. If the project experiences a cost overrun of $100,000, what would be the effect on the ROI?

33 / 50

You are a project manager for a manufacturing company. You want to start using activity-based costing instead of traditional costing. Which of the following would be the most beneficial reason?

34 / 50

You are a project manager overseeing a customer service process redesign project. After implementation of activity-based costing, you notice that the cost of 'Ticket Resolution' activity is surprisingly high. What might be the key reason for this?

35 / 50

As a project manager, you have implemented activity-based costing on your project. The project is delayed and over budget. Upon inspecting, you discovered that the activity 'Materials Procurement' is taking much longer and requiring more resources than anticipated. What is the probable cause?

36 / 50

You notice that there are too many non-value adding activities in a manufacturing project you're managing. On conducting a Value Analysis, you find that elimination of these activities would not impact the project's outcome. What should you do?

37 / 50

During a project, you notice that the Cost Performance Index (CPI) is consistently above 1.5. As the project manager, what should be your primary concern?

38 / 50

A project with an initial investment of $400,000 attracts annual cash inflows of $80,000. If the company's ROI expectation is 35%, what measures can you take to achieve this target?

39 / 50

As a CAPM, during the execution phase of your project, you discover that certain low probability risks may potentially come into play, which could impact the costs negatively. What financial measures should you consider to safeguard the project budget?

40 / 50

During cost estimation for a project, you are using the analogous estimating technique. What should you consider when applying this technique?

41 / 50

Your project's key stakeholder suddenly demands a major change that could disrupt the project's timeline. What should you do if you have previously prepared a contingency plan?

42 / 50

As a project manager in a housebuilding project, you've realized that the activity 'Electrical Wiring Installation' isn't in line with calculated costs under activity-based costing. Considering indirect costs from the owner of the building's requirements, what's the best adjustment?

43 / 50

While performing a Value Analysis, you find several small opportunities for achieving cost savings but none of these changes on their own are significant. What should be your approach in this situation?

44 / 50

You are overseeing a software development project with a budget of $500,000 expected to last 10 months. After 5 months, you have spent $300,000 but only completed 40% of the work. What is the Schedule Variance (SV)?

45 / 50

You are assigned to a project with an initial investment of $600,000. The project brings an annual cash inflow of $120,000. If your financial advisor suggests to reach an ROI of 25%, what should be your approach?

46 / 50

Your project has an initial cost of $500,000 and is set to generate a cash inflow of $100,000 annually. If your company's ROI expectation is 40%, how should you adjust the project?

47 / 50

You are a project manager for an Industrial Construction project which was initially estimated to cost $7 Million. During the project, unforeseen soil complications increased the cost by 18%. What is the new cost estimate?

48 / 50

During a cost estimation process for a construction project, the project manager is gathering data on labor costs, material costs, and equipment costs. The project manager is using historical data, expert judgment, and industry benchmarks to develop the estimates. What cost estimation technique is being described in this scenario?

49 / 50

You are managing a project to build a new hospital wing with an estimated cost of $12 Million. Due to a delay in receiving certain materials, an increase in cost of 15% is anticipated. How much is the new cost estimate?

50 / 50

You are managing a project to replace an aging server infrastructure. A consultant suggests you consider life-cycle cost to compare on-premise servers, cloud servers, and hybrid solutions. How should you approach this task?

Your score is

0%

 

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!
Scroll to Top