CAPM Exam 5 – Project Scope Management Questions with Answers

CAPM Project Scope Management Exam Questions & Answers

Practice the CAPM Exam 5 – Project Scope Management past questions and answers. Our experts have answered the questions and you will get the correct answers to the CAPM Exam 5 – Project Scope Management questions. Prepare yourself for the exam ahead and test your knowledge and readiness.

0 votes, 0 avg
1

CAPM Exam 5 - Project Scope Management Questions with Answers

Certified Associate of Project Management

CAPM Exam 5 - Project Scope Management Questions with Answers

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 40

A project manager discovers that her project has a planned value of $200,000, an actual cost of $220,000, and an earned value of $210,000. What does this information tell about the project's status?

2 / 40

In a hardware development project, the earned value is found to be $8,000, and the actual cost is $10,000. However, the planned value was only $7,000. What does this tell about the project's status?

3 / 40

A project manager is reviewing the Project Scope Statement for a new software development project. Which of the following elements is most critical to include in the statement?

4 / 40

As a project manager you are given a project that has already begun. In your review, you find out that the scope baseline had developed without any formal sign-off process. What should you do?

5 / 40

During the project scope verification process, a team member identifies a key deliverable that is not thoroughly implemented. However the deadline is closing in. What would be your course of action as a project manager?

6 / 40

Notice a number of requirements in your project are deemed 'Nice-to-Have' by stakeholders, which could potentially delay the project. As a project manager, how should you handle this case?

7 / 40

In an infrastructure project, you discover that the quality standards for the requirements have been majorly overlooked. A large part of the project work has been completed. As a project manager, what would be the best course of action?

8 / 40

In a project where the Cost Performance Index (CPI) is 0.9 and the Schedule Performance Index (SPI) is 1.1, what does the variance analysis suggest?

9 / 40

During a project to develop a new mobile app, the product owner proposes adding a feature that was not part of the original product scope but could potentially increase user engagement. As the project manager, what should be your first step?

10 / 40

You are managing a project to transition an organization's manual record keeping to a digital system. A crucial stakeholder insists on including a feature that will significantly impact the budget but this was not part of the initial project charter. How should you address this new requirement?

11 / 40

You're managing a project where a detailed project plan wasn't made and now you're seeing low quality deliverables produced as a result. What can be your best approach to control this?

12 / 40

Which phase of the project life cycle is typically characterized by the highest level of effort and resource consumption?

13 / 40

You are a project manager and you have just received a significant project deliverable. What is the next step you should consider?

14 / 40

Project manager Alex is working on a building project with a planned value of $200,000. The actual cost is $175,000 and earned value is $185,000. What is the project’s cost and schedule performance?

15 / 40

Which phase of the project life cycle is typically characterized by the highest level of effort and resource consumption?

16 / 40

While conducting a scope verification, you observe that an important documentation relevant to the project scope is missing. What would be your next step as a project manager?

17 / 40

You, as the project manager, are presented with an actual cost of $100,000. The earned value obtained is $200,000 but the planned value states as $300,000. How would you respond based on the variance analysis?

18 / 40

As a project manager, you discover midway that a team member is using an unauthorized process to get the job done faster. The process can be beneficial if reviewed and approved. What should you do?

19 / 40

Alan, a project manager, realizes that the planned value of a certain project is $40,000, the actual cost is $50,000 and the earned value is $45,000. What could be the best step for Alan to take?

20 / 40

During the initiation phase of a project, the project manager is reviewing the Project Charter with stakeholders. The Project Charter is a document that provides authorization to start a project, outlining the project objectives, scope, and stakeholders involved. It is crucial for setting the foundation for the project and ensuring alignment with business goals. Which of the following is NOT a key component typically included in a Project Charter?

21 / 40

During scope verification, you discover that a deliverable has been implemented differently from the original project scope but provides additional value. What should be your primary action as a project manager?

22 / 40

A project manager is working on a commercial infrastructure development project. During the planning phase, she realizes that the project scope statement lacks some crucial aspects which could affect the completion of the project. How should she handle this situation?

23 / 40

During a recent project assessment of the software development, the planned value was $40,000. However, there was an actual cost of $60,000 while the earned value was at $45,000. What do these values suggest?

24 / 40

What is the primary purpose of defining the product scope in project management?

25 / 40

Your project is in execution phase, a stakeholder requests a change that is not aligned with the scope baseline. The new addition has the potential to unbalance the project's performance. What should you do?

26 / 40

In the middle of the project, the project manager realizes that the team is working on activities that were not part of the Project Scope statement. What should the project manager do?

27 / 40

You have completed a software deliverable and conducted tests which turned out to be successful. However, the client rejects it after their end-user testing. What could be the reason?

28 / 40

Your design project has an earned value of $20,000, with a planned value of $25,000. Your actual costs are $22,000. What should you do as a result?

29 / 40

During a project status meeting, the earned value is calculated to be $120,000, the planned value is $110,000, and the actual cost is $115,000. What would be your immediate action as a project manager?

30 / 40

In a software development project, a key stakeholder requests a major change that was not included in the original project scope statement. What is the first thing the project manager should do?

31 / 40

You're in the 'monitoring and controlling' phase of your project and you observe that the project cost is exceeding its budget limitations. Considering your project is significantly dependent on the budget, what should be your approach?

32 / 40

During a project, the client repeatedly requests additional features that were not in the original scope. What is the most effective way to manage this potential scope creep?

33 / 40

You are leading a project to develop a new HR system. While testing it, your team identifies an additional feature that can be added, but it wasn't written in the initial scope agreement. As a Project Manager, what should be your next step?

34 / 40

In the middle of a software implementation project, you come to know that the team has been working on tasks that are out of the project scope. You find that these tasks are beneficial but were not identified during the planning phase. How should you handle this situation?

35 / 40

In a project, a significant amount of additional requirements were requested after the planning phase. As a project manager, what should be your plan of action?

36 / 40

You notice that the client keeps suggesting new features during your weekly updates and already implemented features are frequently being modified. What could be the best step to prevent scope creep arising from this situation?

37 / 40

John is a project manager who is overseeing a construction project. Unfortunately, upon reviewing the deliverable, they see a mismatch with the planned blueprint. What should he be doing?

38 / 40

You discover a change in project scope that could enhance project value, but it was not approved officially. What should be your next action?

39 / 40

A project has a planned value of $75,000, an actual cost of $70,000 and earned value of $80,000. As a project manager, how would you interpret these data?

40 / 40

Which of the following is considered the most critical component of the scope baseline for measuring project performance?

Your score is

0%

See also:

CAPM Exam 8 – Project Cost Management Questions with Answers

CAPM 7 – Project Time Management Questions with Answers

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!
Scroll to Top