CAPM 7 – Project Time Management Questions with Answers

Practice the CAPM 7 – Project Time Management past questions and answers. Our experts have answered the questions and you will get the correct answers to the CAPM 7 – Project Time Management questions. Prepare yourself for the exam ahead and test your knowledge and readiness.

0%
0 votes, 0 avg
0

CAPM Exam 7 - Project Time Management Questions with Answers

Certified Associate of Project Management

CAPM Exam 7 - Project Time Management Questions with Answers

Questions will be picked at random from the question bank.

You can use the NEXT button to move to the next question, use the PREV button to move to the previous question, the CLEAR button to clear any answer of your choice and you have the FINISH button to end the exam if you choose to.

Any question not answered before the end of the exam time, will be marked as wrong and the exam will end by itself. So try to attempt all questions on time.

Goodluck!

1 / 50

You are managing a complex project with several critical paths. The shortest critical path has a total float of 4 days. If a task on this path gets delayed by 5 days, what will be the impact on the project deadline?

2 / 50

You're managing a project with unfamiliar activities. An expert suggested the use of an estimation technique that uses weighted averages of optimistic, pessimistic, and most likely estimates. What technique is he suggesting?

3 / 50

An automobile manufacturer has redundant resources causing a significant increase in operational costs. As a Project manager, how can you optimize these resources?

4 / 50

Your project is in the final stage. However, the remaining time is less than the estimated task duration for the final task in the critical chain. What is the recommended approach in CCPM?

5 / 50

Question: Amy is managing a project with the estimated optimistic time 6 days, pessimistic time 14 days, and most likely time 8 days. How should Amy compute the expected project time using PERT Analysis?

6 / 50

Alice is handling a project with an estimated optimistic time of 7 days, a pessimistic time of 20 days, and a most likely time of 11 days for task B. Using PERT Analysis, What should be the estimated expected time for task B?

7 / 50

You are handling the product development project of a smart device. Its features are yet to be finalized owing to rapidly changing market trends. How can Rolling Wave Planning aid this project?

8 / 50

Your team is working on a project with tight deadlines. During the planning phase, you realize that some activities can be carried out in parallel to save time. Which technique would you apply?

9 / 50

The CPI of your project is currently at 1.3, but the project is still under schedule stress, with SPI at 0.8. What would your best course of action be?

10 / 50

Your team is working on the development of a new mobile application. During the activity definition, you notice that app testing could begin before all development activities are completed. What method should you apply?

11 / 50

Bob is a project manager who has run a PERT analysis on her project. A task has been found with an optimistic time of 4 days, a pessimistic time of 16 days, and a most likely time of 7 days. How should Bob calculate the expected time for this task?

12 / 50

There is a project with uncertain activity durations due to the possibility of resource allocation changes. What is the best estimation method to handle these situations?

13 / 50

Anna is managing a digital transformation project. She decides to use the PERT analysis method for task Z, with a most likely time of 15 days, an optimistic time of 10 days, and a pessimistic time of 25 days. What would be the expected time for task Z?

14 / 50

You are managing a large construction project. Midway through, you realize that you need to revise and add new activities to the project. What should your first step be?

15 / 50

You are handling an agile software development project. The initial sprint was successful but the client is likely to introduce several changes in the upcoming sprints. How should you apply Rolling Wave Planning?

16 / 50

You are managing a software development project. The senior developer informs you that writing unit tests should happen before the code is integrated with the rest of the system. However, your project plan has these tasks scheduled the other way around. What should you do?

17 / 50

While monitoring, you notice a specific task repeatedly causing delay due to longer than estimated setup time. What could be a good solution?

18 / 50

You are managing a project in a field in which you have extensive experience. You understand the tasks and their duration required. Which approach would you primarily use?

19 / 50

In your project, the last few tasks are consuming buffer faster than estimated. The project deadline is closing and only one non-critical task remains. What's your best step forward?

20 / 50

You are coordinating a product launch event. You're under pressure and noticed that the product promotion activities are scheduled to start after the product launch. How would you rectify this?

21 / 50

You are coordinating a software product rollout. Task B is critical and has a free float of 0 days. If Task C, which is linked to Task B and is non-critical with a free float of 3 days, is delayed by 2 days, what will be the impact on Task B and the overall project schedule?

22 / 50

A construction firm is experiencing delays due to inadequate labor allocation. The Project Manager determines that this is largely because the allocation was based on the availability rather than the skills of the resources. What would be the best approach to optimize resource utilization in this scenario?

23 / 50

Question: Peter is managing a project with a tight budget. He has completed a PERT analysis and calculated the standard deviation for each activity. How can he utilize this information?

24 / 50

In Critical Chain Project Management, what is the role of a project buffer?

25 / 50

During project planning, a project manager is tasked with sequencing activities. In a construction project, the project manager needs to determine the order in which activities should occur to minimize delays and ensure efficiency. One critical activity is pouring the foundation. What is the best practice for determining the sequence of activities in this scenario?

26 / 50

You've been given a project with distinct activities that need to be performed in sequence. Which method should you use to estimate the duration of these activities?

27 / 50

You are managing a start-up project where the business model and revenue generation strategy will evolve over time based on customer response and market analysis. How should the Rolling Wave Planning be implemented in this case?

28 / 50

You are managing a construction project. After reviewing the project plan, you see that laying the foundation is scheduled after erecting the building walls. What would you do?

29 / 50

You are part of a project with tight deadlines. The project has a total float of 1 day. If a noncritical task with a total float of 3 days gets delayed by 2 days, what does this imply?

30 / 50

Question: Jack is using PERT Analysis for his software project involving various complex tasks. For task X, the optimistic time is 5 days, the pessimistic time is 20 days, and the most likely time is 10 days. What is the variance for this task?

31 / 50

You are managing an infrastructure project. The project has a total float of 10 days. If a critical task within this project is delayed by 15 days, what will be the effect on the project completion date?

32 / 50

You are behind schedule on a critical path of your project. In order to make up for lost time, what technique can be used?

33 / 50

Question: Carla is undertaking a high risk project with a highly uncertain completion time. Should she use the PERT analysis method?

34 / 50

You are the project manager assigned to a construction project. After the work breakdown structure (WBS) is completed, you realize the task of getting clearance takes longer than estimated. How should you adjust to this sudden change?

35 / 50

A software development project you’re managing is exceeding its budget due to inefficient resource usage. The project has several team members who are specialized in specific areas, but they often sit idle because their specific skills are not required all the time. How can you adequately address this?

36 / 50

A financial institution's IT team has a higher than usual server downtime, leading to inadequate service delivery. What would be the best way to optimize resource management in this scenario?

37 / 50

You're managing a project to develop an Artificial Intelligence model. Given the nature of the project, there is a significant level of uncertainty around the time each development phase may take. How would you manage using Rolling Wave Planning?

38 / 50

You are responsible for managing a large data migration project. Before finalizing the activity list, you realize the need for an additional server setup. What should be the best approach to handle this?

39 / 50

You are part of a team working on a year-long infrastructure project. The first phase progress has revealed new hurdles for the next phase. How should you utilize Rolling Wave Planning?

40 / 50

In a project network diagram, Task A has a total float of 5 days and Task B, which is dependent on Task A, has a total float of 2 days. What is the relationship between the free float of Task A and its total float?

41 / 50

You are managing a software upgrade project. You realize the software debugging is taking place after the software upgrade. What is the best course of action?

42 / 50

You have been asked to use the Rolling Wave Planning technique for a new project. When does this technique prove most useful?

43 / 50

Looking at the Gantt chart, a project manager notices a task is stretching beyond its deadline due to unplanned breaks. How should this be handled?

44 / 50

You are leading a project with tasks that have been performed regularly in prior projects. You need an estimation method that can provide quick and reasonably accurate results. What technique should you primarily use?

45 / 50

A logistics firm wants to optimize its fleet management to better serve its customers and reduce idle time. What's the best approach in this scenario?

46 / 50

A software company is often delayed in their projects due to inadequate resources. What's the most suitable strategy, in this case, to ensure resource optimization?

47 / 50

You are managing a project that aims to launch a new product in the market. The market trends are highly unpredictable and the product details are yet to be finalized. How would you use Rolling Wave Planning?

48 / 50

Critical path of your project shows a negative total float. What does this mean?

49 / 50

As a Project Manager, you are leading a project to build a website for a client. After mapping out all of the tasks, you identify several tasks that can be worked concurrently. What would be the most effective way to organize your plan?

50 / 50

You have just completed the Work Breakdown Structure (WBS) for a complex software development project. However, the project team is unable to understand some of the activities. What should be your next step?

Your score is

0%

 

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected !!
Scroll to Top